Code Description Qty Unit Unit Cost Tax Cost Comment
0400 - Framing Framers Labour Quote 1.000 Lot $ 800.00 $ 0.00 $ 800.00
0400 - Framing Truss Package 1.000 EA $ 425.00 $ 21.25 $ 446.25
0300 - Steel 3/4" Bolt 6.000 EA $ 2.30 $ 0.69 $ 14.49
0300 - Steel Telepost 54in - 100in 1.000 EA $ 70.71 $ 3.54 $ 74.25
0200 - Concrete Concrete Material - Slab 1.403 m3 $ 300.00 $ 21.05 $ 441.99
0200 - Concrete Rebar - Slab 107.149 kg $ 2.50 $ 13.39 $ 281.27
0200 - Concrete Finishing Labour - Slab 12.555 m2 $ 1.00 $ 0.00 $ 12.55
0200 - Concrete Vapour Barrier Below Slab 135.141 ft2 $ 0.06 $ 0.41 $ 8.51
0200 - Concrete Concrete Material - Walls 4.339 m3 $ 300.00 $ 65.09 $ 1,366.84
0200 - Concrete Rebar - Walls 331.354 kg $ 2.50 $ 41.42 $ 869.81
0200 - Concrete Concrete Labour - Walls 19.413 m2 $ 5.00 $ 0.00 $ 97.06
0200 - Concrete Concrete Material - Footings 0.910 m3 $ 300.00 $ 13.65 $ 286.68
0200 - Concrete Rebar - Footings 69.497 kg $ 2.50 $ 8.69 $ 182.43
0200 - Concrete Labour - Footings 4.072 m2 $ 1.00 $ 0.00 $ 4.07
0400 - Framing 2x8 166.162 ft $ 0.80 $ 6.65 $ 139.58
0400 - Framing 2x8 Treated Sill 27.495 ft $ 1.10 $ 1.51 $ 31.76
0400 - Framing 3/4 Plywood Subfloor 5.336 Sheet $ 33.60 $ 8.96 $ 188.24
0400 - Framing Screws for Subfloor 244.470 EA $ 0.03 $ 0.37 $ 7.83
0300 - Steel Steel-Beam 201.774 kg $ 3.75 $ 37.83 $ 794.49
0200 - Concrete Base Gravel Material 2.726 m3 $ 17.00 $ 2.32 $ 48.66
0200 - Concrete Base Gravel Labor 17.989 m2 $ 1.00 $ 0.00 $ 17.99
0400 - Framing Framing-2x6 Material 282.788 ft $ 0.63 $ 14.25 $ 192.41
0400 - Framing 2x10 28.177 ft $ 1.14 $ 1.61 $ 33.73
0400 - Framing 3/8 OSB Wall Sheathing 7.531 Sheet $ 10.61 $ 4.00 $ 83.90
0400 - Framing Nails for Wall Sheathing 345.074 EA $ 0.03 $ 0.53 $ 11.05
0400 - Framing 2x4 208.490 ft $ 0.33 $ 3.44 $ 72.24
0400 - Framing 7/16" OSB Sheathing 3.104 Sheet $ 10.98 $ 1.70 $ 35.79
0400 - Framing Nails for Roof Sheathing 142.218 EA $ 0.03 $ 0.22 $ 4.55
$ 272.55 $ 6,548.41
Sorting

Click the column headers to sort. Multi-column sorting can be performed by holding the SHIFT key and clicking more than one column header.

Search and Filter

Enter text in the search field to filter the report.

Column Re-ordering

Columns in Component Reports only may be re-ordered by clicking and dragging the column header. The order of the columns will persist until the selected fields are modified using the Report Setup Dialog. Columns for the other report types can not be re-ordered.

Copy Button

Copies the filtered table rows to the clipboard. The header will not be included.

Print Button

Exports the filtered table rows in a separate window and invokes the browser Print command.

CSV Button

Exports the entire table to a CSV file that may opened in Excel. Filters and column sorting are ignored.